Pembina approves power plant and joins pipeline initiative
Tap title to read story
Calgary, Canada — Pembina Pipeline on July 2 approved a final investment decision to construct the C$4.6 billion Greenlight Electricity Centre, a 932‑megawatt gas‑fired plant in Sturgeon County to power an unnamed hyperscale data centre, and concurrently entered a non‑binding heads of agreement to participate in a proposed one‑million barrels‑per‑day pipeline and export terminal project.
The announcements this week name partners for the power project including Morgan Stanley Infrastructure Partners and Kineticor Asset Management and list federal and Alberta government entities plus Trans Mountain among pipeline participants; Pembina says both initiatives remain subject to regulatory approvals, commercial agreements and conditions and could affect regional energy infrastructure and market access timelines in the coming years.
Timeline
- 1. Prior to July 2026: Canada has five functioning hyperscale data centres; demand for data centre capacity rises with AI and cloud growth.
- 2. July 2, 2026: Pembina announces positive final investment decision for the C$4.6 billion, 932 MW Greenlight Electricity Centre in Sturgeon County.
- 3. July 2, 2026: Pembina signs a non-binding Heads of Agreement with federal and Alberta entities, Trans Mountain and others for a proposed ~1,000,000 bpd pipeline system and terminal.
- 4. Following announcements: Pembina names partners for the power project (Morgan Stanley Infrastructure Partners and Kineticor Asset Management) and confirms projects are subject to conditions and approvals.
- 5. Next steps: Regulatory review, commercial contracting for the data centre off-taker, Indigenous participation discussions, and further planning for pipeline development.
Sources
JQJO Editorial Desk · Human reviewed · AI assisted. Report a correction.